Projects - Energy

Client: Holcim Vietnam Co., Ltd
Location: Hon Chong, Vietnam
Date: June 2006 – November 2008
Project Objective: Design, Supply, Installation, Testing & Commissioning to switch the main power source of Hon Chong Holcim Cement Plant from 6.6KV diesel power plant to 110KV power grid of electricity of Vietnam, while keeping the power plant as backup.

Client: Kampot Power Plant Co., Ltd
Location: Kampot province, Cambodia
Date: April 2006 – April 2007
Project Objective: Design, supply, built a 23 MW power plant in Consortium with our partner Wärtsilä Finland

Client: Cambodia Electricity Private Co. Ltd (CEP)
Location: Phnom Penh, Cambodia
Date: May 2005 – May 2006
Project Objective: Engineering Design, supply and build a 48 MW power plant with our consortium partner Wärtsilä Finland Oy, Procurement and Construction

Client: Khmer Electrical Power Co. Ltd
Location: Phnom Penh, Cambodia
Date: April 2004 – March 2005
Project Objective: Engineering
Procurement and Construction, Design, supply and build a 30 MW power plant with our consortium partner Wärtsilä Finland Oy

Client: Ministry of Industry, Mine and Energy
Location: Sihanoukville, Cambodia
Date: September 2002 – June 2003
Project Objective: Supply, Installation, Testing and Commissioning, Electrical installation of the rehabilitated water treatment plant