Kampot Power Sub-Station Cambodia

Client: Electricite Du Cambodge

Location: Kampot province, Cambodia

Date: August 2010 – February 2012

Project Objective: Engineering, Design, Manufacturing, Transportation, Erection, Installation, Testing and Commissioning of 230kV electrical substation works on a turnkey basis

Scope of works: 

  • Civil Works

Design, and construction of concrete foundations, steel support structures, fencing, concrete cable trench, substation drainage system, concrete road, asphalt road and buildings such as control building, warehouse, guard house

  • Electrical Works

Design, supply, install, testing and commissioning of primary 230kV system with secondary system (Control and Protection)

  • SCADA works (Supervisory Control And Data Acquisition)

BCU (Base control units), and computerized control system, which control and monitor the substation

  • Telecommunication Works  

SDH (Synchronous Digital Hierarchy) system, PABX, connecting electrical substations of EDC, up to National Control Center (NCC)

  • MEP works (Mechanical, Electrical, and Plumbing works)  

Design, supply, install, testing and commissioning of building services including indoor and outdoor lighting, fire alarm and firefighting system, security monitoring, low voltage distribution panels, air-conditioning, waste water system, clean water system