Client: Sonja Kill Foundation (Germany)
Location: Kampot Province, Cambodia
Date: April 2007 – June 2009
Project Objective: Design, Supply, Installation, Testing & Commissioning, Complete a hospital for children project in Cambodia with the construction of an operation theatre, a maternity building and 23 supporting buildings
Scope of works:
MV System: MV switchgear – SM6 22kV 630A, 1 Transformer 1000 kVA, MV cable and accessories LV System with metering panel, 2 400kVA gensets, synchronized panel, main switch board, distribution panels, power & control cables, electrical PVC & HDPE conduits, hotdip galvinez. Cable tray, UPS 80kVA, Incinerator capacity 400kg, 2 compartments PVC trunking, Socket Outlets, Lighting Switches, Cleanroom lightings & indoor & outdoor lightings, Grounding & lightning protection system
Single split A/C system including 76 sets of standard hi wall and under ceiling split capacity 2.57kW to 6.45kW Ceilng fans (245 sets)
Fresh air & exhaust system with fans, ducting, flexible and grilles
Clean room central split ducting including 2 sets of AHU-CDU capacity 114 kW & 21 kW and ducting, flexible, dampers, heater, manometer, supply & return grilles, BMS control system for operation theater & maternity building
Telephone system: PABX with 260 extensions, MDF, TPEV & TIEV cables and telephone sockets Data system: 24 -16 ports switches, 19” Close Rack, Cat6 cables and data sockets, CCTV system