Sotelco Data Centre

Client: Sotelco Ltd._Beeline Cambodia (former subsidiary of VimpelCom Ltd.)
Location: Phnom Penh – Cambodia

Date: October 2008 – February 2009

Project Objective: To complete in only 6 weeks, the installation of security systems, main electricity supply with a precise control of temperature and hydrometry for a 800 sqm warehouse for equipment storage.

Scope of works:

  • Civil Works, Design & Build

Re-enforced concrete work – foundation for all technical equipment and technical building structure Re-habilitation with steel structure beams (20m span) for 800sqm area without any column, to support 2 layer-gypsum ceiling with insulation and technical equipment above. 

Waterproofing on concrete surfaces of roofs. 

Walls, ceiling, floors, doors, windows work with insulation on the 3,500sqm office area 

Raised floor for data centre, Finishing and architectural work (paint, tiles, office curtains)

Get In Touch

WE BUILD WHAT YOU DREAM